Control Example: Time Spent Out Of Control

In this example, we see if our machine is maintaining the oven temperatures we are targeting.

Available Information

AssetPropertyDesc
Finish Oven Zone 1Temperature - OvenThe actual temperature of our oven
Finish Oven Zone 1Temperature - TargetThe expected temperature of our oven

Initial Layout

To begin with, we have one Control Output node, one Control node and two ARDI Point nodes.

Step 1: Determine Control

Step 2: Tune

When we save this and look at the report, we can see that it's almost always out of control.

This might be true, or it might mean that our tolerances could be a bit too strict.

If we go in and update our span to be within 5 degrees of the target instead of 1, we get the results below…

This is better but still not great. Either our oven is having real issues, or we need to refine our logic further.

We can see a lot of noise - going in and out of control very frequently. But there's the opportunity to remove some of these small periods of control loss with a timer.

This updated logic tells the system that the measurement has to be uncontrolled for four seconds before it's considered being genuinely out of control.

The Results

This results in a chart that is far less noisy, although still showing some issues.

Deployment Options

Control charts have one of the largest lists of deployment options.